Timeline for constructing G+3 in 60*40 site.

Post Reply
msg5555
Posts: 10
Joined: February 25th, 2022, 4:08 pm

Timeline for constructing G+3 in 60*40 site.

Post by msg5555 »

Planning on building a G (Parking) +3 Floor home.

Was wondering the timeline and approximate costs for a decent quality home.

I understand that sky is the limit for interiors.

With steel and cement at all time highs wanted to revisit the costing.

Thanks for your time.
msn1270
Posts: 1523
Joined: June 17th, 2009, 2:21 pm

Re: Timeline for constructing G+3 in 60*40 site.

Post by msn1270 »

Hi

Just mentioning G+3 floor is not sufficient. You also need to specify approximately how much area in Squares you are planning to construct to estimate the price.

For timeline, you can consider approx. 1.5 to 2 years as the timeline for the construction. Many builders promise to complete in 1 year in the initial days, but always there are many hurdles in the construction period. Wall Structure is phase 1 & Once the structure is ready, Phase 2 takes more time for arranging & synchronising different labour teams for Wood work, Flooring, Plumbing, electrical, Painting, Fabrication,,,etc.

With todays increasing raw material prices. Keep an average of Rs. 2,500 as the rate per square feet of construction for a descent quality. if anyone quotes Rs. 1,500 to 1,800 per square feet, definitely it will be a misguiding number & raises question on their quality of construction and also lot of hidden things will be there, which they'll not disclose in the initial quote & they add all those activities as additional charges, which doesn't cover under standard package.
Last edited by msn1270 on April 8th, 2022, 2:47 pm, edited 1 time in total.
msg5555
Posts: 10
Joined: February 25th, 2022, 4:08 pm

Re: Timeline for constructing G+3 in 60*40 site.

Post by msg5555 »

Thanks for your response.

Apart from parking we are planning to have a built area of 6000sqft.
msn1270
Posts: 1523
Joined: June 17th, 2009, 2:21 pm

Re: Timeline for constructing G+3 in 60*40 site.

Post by msn1270 »

Including Parking Consider an average area of 8,000 sq. ft.
you can say 8,000 X 2,500 = 2 Crores as the approx. construction cost.
msg5555
Posts: 10
Joined: February 25th, 2022, 4:08 pm

Re: Timeline for constructing G+3 in 60*40 site.

Post by msg5555 »

Do we have a thread to understand the terms used in construction. So many of the words are alien.
sunil18vns
Posts: 61
Joined: February 10th, 2013, 10:06 am

Re: Timeline for constructing G+3 in 60*40 site.

Post by sunil18vns »

msg5555 wrote:
April 8th, 2022, 9:22 am
Planning on building a G (Parking) +3 Floor home.

Was wondering the timeline and approximate costs for a decent quality home.

I understand that sky is the limit for interiors.

With steel and cement at all time highs wanted to revisit the costing.

Thanks for your time.
A decent quality with JSw steel, birla super cement, kajaria tiles, jaquar etc will be 2000 rs psft
kumar.deni
Posts: 21
Joined: October 1st, 2016, 5:32 pm

Re: Timeline for constructing G+3 in 60*40 site.

Post by kumar.deni »

msn1270 wrote:
April 8th, 2022, 2:46 pm
Including Parking Consider an average area of 8,000 sq. ft.
you can say 8,000 X 2,500 = 2 Crores as the approx. construction cost.
Hi,
can you kindly share your bescom transformer experience, some details on what does it include and pricing
Thank you
Post Reply