Finally Started my construction a Duplex 30X50 site in EC...
Re: Finally Started my construction a Duplex 30X50 site in E
2nd floor room construction in progress and ground floor electrical work (Anchor metal boxes, VIP pipes, DB box indo asian)
@ Ausaraj - Was not able to track the cost, I have paid almost 50% of the total construction amount.
@ Ausaraj - Was not able to track the cost, I have paid almost 50% of the total construction amount.
- Attachments
-
- Electrical items
- Electrical items.jpg (274.74 KiB) Viewed 7772 times
-
- 2nd floor Room
- 2nd floor room 2.jpg (333.9 KiB) Viewed 7772 times
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Current Completion view
- Attachments
-
- View 2
- House View 3.jpg (233.15 KiB) Viewed 7771 times
-
- View 2
- House View 2.jpg (225.85 KiB) Viewed 7771 times
-
- View 1
- House View 1.jpg (224.25 KiB) Viewed 7771 times
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Martin,
good to see the progress.
good to see the progress.
Re: Finally Started my construction a Duplex 30X50 site in E
Hi Martin, for electrical fittings and accessories you can go to surya traders which is in doddatogur. Hardly 3 to 4kms from huskur gate. After researching so much i found this shop and he is authorized dealer of legrand, anchor, cona, vguard etc. Prices are reasonable. He gives 3 or 4 percent cheaper comparing to all other local shops.
Note: People who want to buy CFL lights, please go to metro cash and carry. There you get the cfl lights for 85rs and the same cfl costs 150-180 in outside market. I brought all CFL bulbs from metro
Note: People who want to buy CFL lights, please go to metro cash and carry. There you get the cfl lights for 85rs and the same cfl costs 150-180 in outside market. I brought all CFL bulbs from metro
-
- Posts: 52
- Joined: September 25th, 2013, 12:39 pm
Re: Finally Started my construction a Duplex 30X50 site in E
Adding to what Rajesh said, Star Bazzar is selling philips CFL 27 watts bulsbs at buy one and get one free offer, check it out.
Re: Finally Started my construction a Duplex 30X50 site in E
Hi,
I looked at the plan. Can you confirm that the dimensions mentioned in the floor plan are inclusive of walls or they are what you will see inside.
So the 2150 is net carper area which they charge or gross area?
I looked at the plan. Can you confirm that the dimensions mentioned in the floor plan are inclusive of walls or they are what you will see inside.
So the 2150 is net carper area which they charge or gross area?
Re: Finally Started my construction a Duplex 30X50 site in E
Thanks Pooja.
@rajesha07 - I had given my contractor details on Surya Traders. I tried to get their number from Just Dial I got some Surya electricals (Begur Road). he was giving 60% on suitable and 40% on original Anchor boxes... However the contractor got the original one from Hosa road at 60% discount. Since its a material i have left it to the contractor to decide where he wants to buy. But while buys electrical equipments like fan, geyser etc have to do some research on this site
@pchowhan - The dimensions include the wall. 2150 is the gross area i guess.. I have made some changes so final dimensions will differ.
@rajesha07 - I had given my contractor details on Surya Traders. I tried to get their number from Just Dial I got some Surya electricals (Begur Road). he was giving 60% on suitable and 40% on original Anchor boxes... However the contractor got the original one from Hosa road at 60% discount. Since its a material i have left it to the contractor to decide where he wants to buy. But while buys electrical equipments like fan, geyser etc have to do some research on this site
@pchowhan - The dimensions include the wall. 2150 is the gross area i guess.. I have made some changes so final dimensions will differ.
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Update on the loan status from AXIS Bank.. I had submitted the request for disbursement last week this was for Roof area, plus the 2nd floor room...
To my shock they have approved only 1 Lakh.
Below was the estimate i sent them and asked for reassessment ----- However they came back telling thats something not in their control and have to go by what the assessor has given as estimate.....
Total Material used for 2nd Floor Roof Slab
1) 94 Bags cement
2) 500Cft Sand
3) 2.4 Tonnes of Steel
4) 1 and ¼ load of Jelly
5) Centering charges
6) Gange people Charges
7) Leveling mason charges
8) Electrical piples
Total material used for 2nd floor tank room
1) Cement 20 Bags
2) 200 Cft Load sand
3) .5 Tonnes of steel
4) 500 Bricks
5) Mason Charges
6) Jelly for Pillar
Electrical work
1) Cutting work completed on ground floor
2) Bought pipes and boxes
To my shock they have approved only 1 Lakh.
Below was the estimate i sent them and asked for reassessment ----- However they came back telling thats something not in their control and have to go by what the assessor has given as estimate.....
Total Material used for 2nd Floor Roof Slab
1) 94 Bags cement
2) 500Cft Sand
3) 2.4 Tonnes of Steel
4) 1 and ¼ load of Jelly
5) Centering charges
6) Gange people Charges
7) Leveling mason charges
8) Electrical piples
Total material used for 2nd floor tank room
1) Cement 20 Bags
2) 200 Cft Load sand
3) .5 Tonnes of steel
4) 500 Bricks
5) Mason Charges
6) Jelly for Pillar
Electrical work
1) Cutting work completed on ground floor
2) Bought pipes and boxes
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Has your contractor taken more money than the construction done? This could be a real possibility and is a common malpractice by contractors.
Re: Finally Started my construction a Duplex 30X50 site in E
Its the other way round, I have not made payments as per the schedule.. Thankfully he is doing in his own investment. Waiting for the bank issues to be resolved to get back on track with payments as committed.