Foundation cost/compound wall

sam_m400
Posts: 493
Joined: April 6th, 2010, 2:21 pm

Foundation cost/compound wall

Post by sam_m400 »

Hi All

My contractor saying the following rate

digging - 6 Rs
foundation stone work - 40 Rs per Sq ft (depth)*total length)
compound wall - 40 rs Per Sq ft (height*total length).

Is this rate prevailing/good one?

Regards
Sam
JollyRogers
Posts: 250
Joined: October 24th, 2010, 6:37 pm

Re: Foundation cost/compound wall

Post by JollyRogers »

Get a JCB to get the earthwork done. You can get them for about Rs.750 per hour. (They need atleast 4 hours of work usually).
This works out half the cost of Rs.6 per sq.ft if done manually.
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Foundation cost/compound wall

Post by maheshvivid2003 »

i had a bad exp with jcb .....u wont get the exact shape sometimes the mesurement size of the footin will increase ....then the material cost will also increase

only thing is u can save lil money n time thats all
sam_m400
Posts: 493
Joined: April 6th, 2010, 2:21 pm

Re: Foundation cost/compound wall

Post by sam_m400 »

Thanks, I also heard the same thing from many other sources as well.
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Foundation cost/compound wall

Post by maheshvivid2003 »

i spent 97 bags of cement for 12 footing bed size 5*6 n 6*7....can anybody share how much cement they used for 12 footing ....
User avatar
jult
Posts: 120
Joined: July 21st, 2012, 3:42 pm

Re: Foundation cost/compound wall

Post by jult »

WHAT IS THE HEIGHT OF THE FOOTING LAID
JollyRogers
Posts: 250
Joined: October 24th, 2010, 6:37 pm

Re: Foundation cost/compound wall

Post by JollyRogers »

I got my site excavation done by JCB. No complaints whatsoever. It all depends on the experience of the person who is operating this.
The entire excavation for 14 pillars and water sump on a 60x40 plot took about 4 hours. Also I hired a guy to do the finishing for the excavation pits. He took 2 days and I think I paid him around 700-800 bucks. Overall I saved over 50% on the cost and the job done in 2 days.
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Foundation cost/compound wall

Post by maheshvivid2003 »

2 feet height.. footing pit size is 6*6 , 7.6*6 n 5*6 as per plan ....my site 30*40 has loose soil

i gave complete earth work for rs 7 per cft .the excators brought jcb did initial digging n finishing touch is done by 3 people

@ JollyRogers how much cement u used for 14 footing bed ?
keerthi.blr
Posts: 72
Joined: May 5th, 2012, 3:46 pm

Re: Foundation cost/compound wall

Post by keerthi.blr »

@mahesh, you will feel better when u know that 8 pillars consumed 90 bags for footing alone.(Excluding pedestal in 30x 40 site) :)
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Foundation cost/compound wall

Post by maheshvivid2003 »

thanks for info keerthi ....:) we sail in same boat