structure drawing - Is it OK ?

Post Reply
ksmanju
Posts: 34
Joined: September 22nd, 2010, 6:50 pm

structure drawing - Is it OK ?

Post by ksmanju »

Dear Sir,

I have constructed approx 1000 sft -2nd floor independent house on existing building on 30' (N-S)x40' (East -west) - going for walls above walls and no pillars.
I have enclosed a hand drawing showing the concealed beams (12mm rods), steel rods (10mm-50 rods along West to east, 8mm rods- 55 rods North-south).
I intend to go for a room with attached bath room of diemnsion 12'x15' on 3rd floor above MBR shown in the drawing(south west).On this room it is proposed to put 3 nos of 1000 Ltrs storage PVC Tanks.
I need following clarifications :
1.With the qty of steel rods put for RCC Mold - takes the load of one more room & storage tanks in south west ?
2.How many days we need to put water for curing on mold ?
3.After how many days from mold casting day- we can remove the centering, shuttering supports.

Thanks in advance.

from

manjuks
Attachments
structure-draw-2ndfloor.pdf
(78.59 KiB) Downloaded 407 times
Post Reply

Return to “Civil Construction”