Temporary BESCOM Connection - 2 KW - 3 Phase - 56 days
Re: Temporary BESCOM Connection - 2 KW - 3 Phase - 56 days
Does anyone know if BESCOM has now made all temporary connections to be only 28 days (i.e. have they cancelled the "56 day" connection ??). My electrician claims so. Anyone ?
Re: Temporary BESCOM Connection - 2 KW - 3 Phase - 56 days
Got a 28 Day Temporary Connection (3 kVa) done last month. My Contractor did it after getting the relevant documents from me.
The Costs are:
1. Meter Purchase – 2445.00
2. Deposit – 9630.00
3. Non – Revenue Charges – 100.00
4. Office Expenses – 2800.00
5. Wooden Box with accessories for fixing the meter – 3800.00
The Costs are:
1. Meter Purchase – 2445.00
2. Deposit – 9630.00
3. Non – Revenue Charges – 100.00
4. Office Expenses – 2800.00
5. Wooden Box with accessories for fixing the meter – 3800.00
-
- Posts: 109
- Joined: August 22nd, 2012, 11:13 pm
Re: Temporary BESCOM Connection - 2 KW - 3 Phase - 56 days
Could you please tell me how many kilowatts electricity is required for G+2 with borewell. Yet to start construction.
How much is the fine if we exceed load? Is KIlowatt enough for the above purpose? The requirement is only for temporary connection.
How much is the fine if we exceed load? Is KIlowatt enough for the above purpose? The requirement is only for temporary connection.
-
- Posts: 8
- Joined: March 30th, 2014, 8:20 pm
Re: Temporary BESCOM Connection - 2 KW - 3 Phase - 56 days
it depends on the HP rating of your borewell motor.milangadakari wrote:Could you please tell me how many kilowatts electricity is required for G+2 with borewell. Yet to start construction.
How much is the fine if we exceed load? Is KIlowatt enough for the above purpose? The requirement is only for temporary connection.
-
- Posts: 109
- Joined: August 22nd, 2012, 11:13 pm
Re: Temporary BESCOM Connection - 2 KW - 3 Phase - 56 days
Mine is texmo 3hp single phase 40 stage hence opted for single phase electricity as recommend by electricians and few others. I believe it depends on depth of borewell. I am going for single phase 2kw. Is that sufficient?
-
- Posts: 8
- Joined: March 30th, 2014, 8:20 pm
Re: Temporary BESCOM Connection - 2 KW - 3 Phase - 56 days
milangadakari wrote:Mine is texmo 3hp single phase 40 stage hence opted for single phase electricity as recommend by electricians and few others. I believe it depends on depth of borewell. I am going for single phase 2kw. Is that sufficient?
it would sufficient. Ideally recommended is about 3Kw as you have a 3 Hp motor and if contractor uses welding or other electric intensive equipments when motor is running your Kw reading would be higher.