Electrical Contractor Required for Residential House Construction

Post Reply
svk63
Posts: 18
Joined: October 29th, 2016, 8:31 am

Electrical Contractor Required for Residential House Construction

Post by svk63 »

I need Electrical Contractor for building my house in North Bengaluru immediately.

Contractor need to be Quality conscious and Team worker.

Need to interact and work with Architect with passion.

Pls contact on Mobile : 9591147400

Tel : 080-23435765
swamy_blr
Posts: 160
Joined: May 20th, 2016, 6:00 pm

Re: Electrical Contractor Required for Residential House Construction

Post by swamy_blr »

Hi SVK63

You can check with our Electrical Contractor Mr. Madhu @ 9844386325, he is knowledgeable and accepts all your requirements.

He stays in Yelahanka and takes care around Hebbal, Sahakar Nagar, Nagawara, HBR Layout.
He charges on SQFT based , Rs. 2000-2200 Per chadra (10 X 10 SQFT), there is no limit on Electrical Points and requirements under Roof.

Additional charges will be for underground digging from Electric Pole depending on distance (Rs 2000 - 5000).


rgds
Swamy
svk63
Posts: 18
Joined: October 29th, 2016, 8:31 am

Re: Electrical Contractor Required for Residential House Construction

Post by svk63 »

Thanks for the info.

Quote is very reasonable.

I will contact him .
User avatar
ardesarchitects
Posts: 1080
Joined: June 20th, 2009, 2:12 pm

Re: Electrical Contractor Required for Residential House Construction

Post by ardesarchitects »

Hi ,svk63
Are you looking for labor electrical contractor or material contractor ?

Regards
Ar.Praveen.N
Ardes Architects and Interior designers
ardesarchitects@gmail.com
www.ardesarchitects.com
facebook.com/ardes.architects
svk63
Posts: 18
Joined: October 29th, 2016, 8:31 am

Re: Electrical Contractor Required for Residential House Construction

Post by svk63 »

I am looking for labour Electrical contractor who need to work with Architect and good in drawing and communication.
ssharma
Posts: 46
Joined: September 25th, 2016, 12:30 pm

Re: Electrical Contractor Required for Residential House Construction

Post by ssharma »

svk63, did you had a chat with Madhu? did you find him satisfactory?
svk63
Posts: 18
Joined: October 29th, 2016, 8:31 am

Re: Electrical Contractor Required for Residential House Construction

Post by svk63 »

Hi Sharmaji

I had chat with Madhu.

I found him unsatisfactory.

He also said he is very busy and not in a position to take any new contract.
swamy_blr
Posts: 160
Joined: May 20th, 2016, 6:00 pm

Re: Electrical Contractor Required for Residential House Construction

Post by swamy_blr »

Hi SVK,

Good that you haven't continued with him, He is so arrogant and we have to work as per his timings. I usually inform him 3-4 days well in advance but didn't turned and will come as per his timings.

Workwise we don't have any complain, his team will do as per the drawings and so far don't have any concerns.

He always busy, might be more Contracts seems to be gone to his head . I didn't liked his attitude. Anyhow we have to complete our Work so adjusting as per his timings.

rgds
Swamy
ssharma
Posts: 46
Joined: September 25th, 2016, 12:30 pm

Re: Electrical Contractor Required for Residential House Construction

Post by ssharma »

Oh thanks for the info guys, I had a chat with him yesterday and asked for prices and stuff. He refused to tell me anything unless I meet him so I thought i'll take a second opinion.

Did you guys use same electrical guy for getting a bescom connxtion and later for work? I'm just beginning construction so electrical work is far down the line.
swamy_blr
Posts: 160
Joined: May 20th, 2016, 6:00 pm

Re: Electrical Contractor Required for Residential House Construction

Post by swamy_blr »

Hi,

Sharma - I suggest you please look out other Electrician who is nearby to your Place.

Yes, We used him for the Temporary Electrical connection as well. BESCOM guys needs one agent to do all the paperwork.
You can't get Connection directly unless you are with some electrician (Might be some adjustments).
Every 28 days this electricians take the reading and make the payment to Bescom (Need to give 400/- per month additional to bill)

Please take care of below requirements
1) KW requirement - Usually they suggest 4KW to 5KW (Go for max 4KW - Each KW costs 3400/-)
2) Ensure you should go with electrician for Materials purchase for Temporary meter connection (Else you get the list of materials), they will fool you.
3) Temporary shed should be constructed before Electrical connection to be given (Check if shed can be done near to the Borewell/construction area which will save you Cable & Connection wire)

rgds
Swamy