Plan To Start Construction
-
- Posts: 59
- Joined: January 11th, 2016, 10:24 am
Re: Plan To Start Construction
Please try to improve the car parking length. you need atleast 16 ft for a big car to fit in length.
Regards,
Sudheer
Regards,
Sudheer
-
- Posts: 59
- Joined: January 11th, 2016, 10:24 am
Re: Plan To Start Construction
Also you can consider having a wash basin under the Staircase for the dining hall
-
- Posts: 71
- Joined: November 6th, 2016, 9:38 am
Re: Plan To Start Construction
Hi Sudheer,sudheerkeshav wrote:Also you can consider having a wash basin under the Staircase for the dining hall
We are planning to build a storage cabinet underneath the stairs.
Also we have no plans of upgrading the car. The plot is in a gated community and we are at the deadend part of the layout. Hence we will be parking it outside the gate.
Re: Plan To Start Construction
If you want you can try my contractor recently completed my house project. He is very decent and genuine guy and quotes reasonable price. I never had any conflict with him and he completed my project in time. He also stays somewhere close to your site.
-
- Posts: 59
- Joined: January 11th, 2016, 10:24 am
Re: Plan To Start Construction
Very nice plan otherwise. All the best.
-
- Posts: 71
- Joined: November 6th, 2016, 9:38 am
Re: Plan To Start Construction
I am getting a quotation on BOQ in the range of 39 lacs to 54 lacs. This is without, kitchen, bathroom, plumbing and electrical works.
-
- Posts: 48
- Joined: September 30th, 2016, 6:31 pm
Re: Plan To Start Construction
39/lacs to 54 lacs is huge difference. What was ur architecture recoomdation from the budget.
-
- Posts: 48
- Joined: September 30th, 2016, 6:31 pm
Re: Plan To Start Construction
I got messages . you can involve ur architect and take review and take a final call. All the best .major price escalation will be on steel and excavation concrete. The basic price of steel is now around 42000 thousands. This three think if you have control ur budget will be perfect. So try to get structural drawings and qty for whole drawings and have control over this items. Then finalize the contract. Otherwise you will have surprise and blame game start.
Re: Plan To Start Construction
Dear Expert,
we are in the process of start the construction. We have obtained the approval, We have done the borewells, applied to get the temporary BESCOM connection. Before starting the construction we are planning to have a formal agreement with the contractor. I have attached a Agreement copy. Can you please review the agreement once and give us your valuable feedback on this? We are giving full contract.
Regards,
Gout
we are in the process of start the construction. We have obtained the approval, We have done the borewells, applied to get the temporary BESCOM connection. Before starting the construction we are planning to have a formal agreement with the contractor. I have attached a Agreement copy. Can you please review the agreement once and give us your valuable feedback on this? We are giving full contract.
Regards,
Gout
- Attachments
-
- Construction Document-v00 4.pdf
- (300.9 KiB) Downloaded 1386 times
-
- Posts: 48
- Joined: September 30th, 2016, 6:31 pm
Re: Plan To Start Construction
kindly attach the structural drawings and architectureal drawings as a encloser of the aggreement