House Construction Experiance
-
- Posts: 20
- Joined: October 10th, 2012, 10:20 pm
Re: House Construction Experiance
Sump capacity is ~8500 Lts..
Plinth Beam with 12*9 size
Plinth Beam with 12*9 size
-
- Posts: 20
- Joined: October 10th, 2012, 10:20 pm
-
- Posts: 20
- Joined: October 10th, 2012, 10:20 pm
Re: House Construction Experiance
Pillars raised to 7 ft along with mud and jelly filling
-
- Posts: 20
- Joined: October 10th, 2012, 10:20 pm
Re: House Construction Experiance
Soil fill completed along with jelly and cement
-
- Posts: 20
- Joined: October 10th, 2012, 10:20 pm
Re: House Construction Experiance
Hi All,
Today started the brick Wall work.
Today started the brick Wall work.
Re: House Construction Experiance
Hi Anil,
Thanks for sharing your Construction experience, It will be eye opener for us as shortly I am also planning to construct House (Looking for Labour Contract).
Since your's is Duplex house, what is approximate budget you planned for your House. How many chadras it is coming (100 SQFT)
thanks
Swamy
Thanks for sharing your Construction experience, It will be eye opener for us as shortly I am also planning to construct House (Looking for Labour Contract).
Since your's is Duplex house, what is approximate budget you planned for your House. How many chadras it is coming (100 SQFT)
thanks
Swamy
Re: House Construction Experiance
Hi Anil,
Congratulations on starting the construction of your new house and all the best !
Swamy,
I recently constructed a duplex house on a 30x40 plot with the entire ground floor dedicated to parking. Including the staircase room and overhead tank room, it will roughly come to 33-34 chadra
Budget depends on a lot of factors esp. what kind of interior and finishing materials you end up choosing. But 2 lakhs per chadra would get you a good finish. I went for a labor contract and though I still spent a little more than 2 lakhs per chadra, I have been able to use good quality materials.
Congratulations on starting the construction of your new house and all the best !
Swamy,
I recently constructed a duplex house on a 30x40 plot with the entire ground floor dedicated to parking. Including the staircase room and overhead tank room, it will roughly come to 33-34 chadra
Budget depends on a lot of factors esp. what kind of interior and finishing materials you end up choosing. But 2 lakhs per chadra would get you a good finish. I went for a labor contract and though I still spent a little more than 2 lakhs per chadra, I have been able to use good quality materials.
-
- Posts: 103
- Joined: April 21st, 2016, 3:35 pm
Re: House Construction Experiance
can you tell me how much ultra tech cement cost per bag ? if we order multiple bags.
-
- Posts: 20
- Joined: October 10th, 2012, 10:20 pm
Re: House Construction Experiance
Hi Swamy,
it will be almost 24 chadras and budget is 60 Lakhs (out of which i have to pay to contractor ~45 Lakhs)
HI keerthi2006 , Since it is full contract , i am not tracking the price of the cement but what i heard is 365 rs per bag if we buy minimum 100 bags
and my mestri insisting to use either Birla or ACC as he is not satisfied with the quality of the cement .. have to decide by this weeked
Thanks,
Anil
it will be almost 24 chadras and budget is 60 Lakhs (out of which i have to pay to contractor ~45 Lakhs)
HI keerthi2006 , Since it is full contract , i am not tracking the price of the cement but what i heard is 365 rs per bag if we buy minimum 100 bags
and my mestri insisting to use either Birla or ACC as he is not satisfied with the quality of the cement .. have to decide by this weeked
Thanks,
Anil
Re: House Construction Experiance
Hi Anil & karjagir
Thanks for the inputs provided, will work out on my budget.... Mine will be around 35 Chadras so budget will be 75 Lakhs +
Regarding the Cement - Your Mestri is right as quality of Ultatech is going down and it is famous mainly because of availability.
Please go with ACC brand as per analysis done it has good composition as well quality wise also perfect compared to Bira/Ultatech.
rgds
Swamy
Thanks for the inputs provided, will work out on my budget.... Mine will be around 35 Chadras so budget will be 75 Lakhs +
Regarding the Cement - Your Mestri is right as quality of Ultatech is going down and it is famous mainly because of availability.
Please go with ACC brand as per analysis done it has good composition as well quality wise also perfect compared to Bira/Ultatech.
rgds
Swamy