Estimate from the contractor

blrsiteseeker
Posts: 508
Joined: July 18th, 2009, 2:23 am

Re: Estimate from the contractor

Post by blrsiteseeker »

m3_07 wrote:In the initial days I did a similar exercise on the cost front for the wooden windows vis-a-vis the UPVC ones. UPVC ones always stood expensive, with the basic models (no grills) - 50% higher. The new models with grills cost even much higher. I am sure everyones agrees that windows with grills are a necessity on the security point of view.
I got UPVC windows, they are expensive compared to wood windows. But they do look really nice and I hope they last long too. Another benefit is they are better insulated and lower maintenance (no need to paint regularly etc.)
pradeepecr
Posts: 191
Joined: February 14th, 2012, 6:22 pm

Re: Estimate from the contractor

Post by pradeepecr »

Hi blrsiteseeker,

Pls let me know, from where you purchased UPVC windows?
how much it cost you for 3 & 2 track window with grill cost you?

Thanks,
Pradeep
krishna.charugundla
Posts: 6
Joined: April 27th, 2014, 6:07 pm

Carpenter needed immediately for window fixing

Post by krishna.charugundla »

Hi All,
Can some one share the contact of Carpenter -who can fix the window shutters.
My mail-id: krishna.charugundla@gmail.com
Earlier guy who had done the window work absconded.

This is towards K.R.Puram side.

As this is bit urgent appreciate early response from the team.

Regards
Krishna
Nivas
Posts: 153
Joined: June 7th, 2012, 12:24 pm

Re: Estimate from the contractor

Post by Nivas »

unfortunate , I am assuming wooden shutters , window fixing is actually the main and difficult work it can comprise almost 80% of the total labour of shutter work, depending on what state of window shutters are. U will see how easily one can show the shutters on ground and abscond by taking full money and giving a picture that the shutter fixing is a small task.

a) just the shutters is done , only wood work, without hinge fixing and glass fixing ( 20% of labour)
b) glass is fixed .
c) setting is done and hinge is fixed, windows are marked( ie which window goes where).
d) high wire act of finally fixing the finished windows , with some final adjustments .
e) the windows marking is wrong or the marking is not understood by a different carpenter. (complication)
f) final fittings of handles and gate hooks and other accessories.

b to f can cost almost 80% of the shutter labour and if there is a complication ...?, what stage is ur shutters ? what did you pay ur carpenter psft?
Kiran Kumar K
Posts: 134
Joined: May 27th, 2013, 8:57 pm

Re: Estimate from the contractor

Post by Kiran Kumar K »

Hi Krishna Sir, please do contact Mr. Deepak 9242107527 & he is near by u r site I think so.
Post Reply