Labour contract rate. Please help.

ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Labour contract rate. Please help.

Post by ramki067 »

Hi,
I am planning to start construction our house after 15 Jan on labour contract. Our site solid ground is 5 feet below road level. Total build area comes to around 1050 feet. We are constructing ground floor only now. The contractor is quoting 33500 per chadra for the following works:
1. For all civil, bartending and centering works which are given below. We have left 2 feet space all round the plot.
a) So he has to construct 2 stone walls as paya walls for compound and brick wall till 3 feet above road level. Totally it will be around 7 to 8 feet and on top of it plinth beam comes.
b) 15000 liter concrete sump,
C) compound.
d) red brick to be used,
e) all round lintel and chajjas as required.
f) roof at 11 feet. 7 feet lintel and 4 or 3 feet above it to make roof at 11 feet.
G) parapet wall
h) churki for mould.
I) overhead tank structure.
J) centering labour cost.
K) barbending labour cost.

Plz inform me as to whether this rate is OK?

Thanks in advance.

Regards
Ramki
Last edited by ramki067 on December 27th, 2015, 3:04 am, edited 5 times in total.
iamveer
Posts: 12
Joined: May 21st, 2014, 11:33 am

Re: Labour contract rate.

Post by iamveer »

Hi Ramki,

Rate is at higher side. Market rate is in range 25-29k at the moment but again depends on the area too. South bangalore is at lower range whereas the rate is pointing north in North bangalore region.

Regards,
Raghuveer
ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Re: Labour contract rate.

Post by ramki067 »

iamveer wrote:Hi Ramki,

Rate is at higher side. Market rate is in range 25-29k at the moment but again depends on the area too. South bangalore is at lower range whereas the rate is pointing north in North bangalore region.

Regards,
Raghuveer
Thanks raghuveer. Any references for any contractors who is in that range?

Regards
Kiran Kumar K
Posts: 134
Joined: May 27th, 2013, 8:57 pm

Re: Labour contract rate. Please help.

Post by Kiran Kumar K »

hi sir in which part of bengaluru u r site located.
ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Re: Labour contract rate. Please help.

Post by ramki067 »

Kiran Kumar K wrote:hi sir in which part of bengaluru u r site located.
Near gottigere, bannerghatta road.
Kiran Kumar K
Posts: 134
Joined: May 27th, 2013, 8:57 pm

Re: Labour contract rate. Please help.

Post by Kiran Kumar K »

Ok sir it is too long to take the job for my people.
Pratap
Posts: 36
Joined: June 1st, 2011, 10:02 pm

Re: Labour contract rate. Please help.

Post by Pratap »

Hi Ramki,

I feel the quote is higher side. I am doing my construction for similar jobs @ 30,000/- in east Bangalore.
ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Re: Labour contract rate. Please help.

Post by ramki067 »

Pratap wrote:Hi Ramki,

I feel the quote is higher side. I am doing my construction for similar jobs @ 30,000/- in east Bangalore.
Hi Pratap,
Feeling warmth to know that because every contractor I am talking is in that 33000 range only.
Could I get your contractor reference?

Thanks.
sarbda
Posts: 35
Joined: June 30th, 2014, 5:30 pm

Re: Labour contract rate. Please help.

Post by sarbda »

Rates are between 27K to 30k in South Bangalore. Let me if you need my labor contractor ref who is right now constructing from me.
ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Re: Labour contract rate. Please help.

Post by ramki067 »

sarbda wrote:Rates are between 27K to 30k in South Bangalore. Let me if you need my labor contractor ref who is right now constructing from me.
HI sardba,

Yes. Plz do provide me his contact. I shall contact him.

Thanks,
Ramki
Post Reply