Hi People,
Can some one post guidelines for all the documentation work required before constructing a house
A Khata
Tax paid receipts
Plan
Plan approval
Documents from BBMP
etc
and also share their experience and cost while getting these done
BBMP documents checklist
Re: BBMP documents checklist
Required for plan approval:
Khata - Not more than six months old
Khata extract - Not more than six months old
EC latest
Sale Deed copy
Latest Tax paid receipt
Copy of approval from BDA etc if BDA \ BMRDA approved
Plan drawn from BBMP registered architect
After plan approval you need to get from BBMP attested copies of plan, building license copy
Other formalities :
Borewell permission - sale deed, EC, application form, affidavit, fees etc. Refer already existing thread on this.
Temporary elctric connection - sale deed, tax paid receipt, approved plan copy,photograph etc
Khata - Not more than six months old
Khata extract - Not more than six months old
EC latest
Sale Deed copy
Latest Tax paid receipt
Copy of approval from BDA etc if BDA \ BMRDA approved
Plan drawn from BBMP registered architect
After plan approval you need to get from BBMP attested copies of plan, building license copy
Other formalities :
Borewell permission - sale deed, EC, application form, affidavit, fees etc. Refer already existing thread on this.
Temporary elctric connection - sale deed, tax paid receipt, approved plan copy,photograph etc