Post Reply
tendlu
Posts: 202
Joined: September 24th, 2010, 3:55 am

SSM required for front gating area

Post by tendlu »

Is SSM foundation required in the entrance parking gate area? I am asking this because SSM is typically used in the compound wall area but not sure whether it is required for the front gate entrance area. In other words, can I do the front gate area without SSM?
mcneha
Posts: 34
Joined: July 15th, 2013, 10:52 am

Re: SSM required for front gating area

Post by mcneha »

Hi!

Doing SSM below the gate, purely depends on the level difference between the road in front of the gate and the area just inside the gate. If more filling is there then SSM is required or else, BBM is enough.

Regards.

CHANDRASEKAR
xxxxxxxxxxxxxxxxxxx
tendlu
Posts: 202
Joined: September 24th, 2010, 3:55 am

Re: SSM required for front gating area

Post by tendlu »

thanks chandrasekar!

the height difference between road in front if gate and just inside the gate is 1.5ft. is SSM required in this case?
mcneha
Posts: 34
Joined: July 15th, 2013, 10:52 am

Re: SSM required for front gating area

Post by mcneha »

Hi tendlu!

Since it is almost the last stage of work, you can do it either with left over bricks or with left over size stones. Take care for the placement of drain covering in front of the gate.

Regards.
CHANDRASEKAR
mcneha
Posts: 34
Joined: July 15th, 2013, 10:52 am

Re: SSM required for front gating area

Post by mcneha »

Hi tendlu!

SSM or BBM is fine, provided you are taking care for the drain slab support.

Regards.
CHANDRASEKAR