Finally Started my construction a Duplex 30X50 site in EC...

m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

7 Feet walls have been constructed. Lintels work to be completed by this week.

@guruprasad7 - With regards to materials used for contruction, The agreement i have with contractor is he will inform me when the new load arrives. Since i stay close in 1 km radius of the construction site i try to visit the site the same day... However with regards to wood and bathroom fittings, Electrical fittings, Flooring i will go along wwith the contractor while purchasing.. But still there are loop holes like the cement + Sand mix ratio, proper curing etc which i have to go ahead with what he says.

@Chida_gs - There are two issues i am facing with bank
1) Delay in disbursement - The problem is i have taken a loan for an axis bank approved agency ( I was not aware of this while taking the loan). Hence my request has to go through them and they receive the DD on my behalf. Lead time in them sending request to Axis bank and lead time for them to give me the DD. Eg last time it took 4 days for the agency to give me the DD.. I have approached Sr Management written to Nodal officer, Sr VP etc.. However what they say is that since i took loan through agency i have follow the same process and cannot be changed.
First disbursement they had a wrong account number on the DD and to change this it took 10 days.

2) Very less amount being approved compared to the progress made.. Right now only around 35 % of amount is approved against the actual cost incurred till now.

I will see how it works for this disbursement and decide whether to change the bank. I am paying pre emi currently for whatever amount disbursed till now.
Attachments
First floor progress
First floor progress
First floor ready for lintels.jpg (240.07 KiB) Viewed 7364 times
7 Feet walls
7 Feet walls
7 Feet walls.jpg (247.02 KiB) Viewed 7364 times
Regards,
Martin
ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Re: Finally Started my construction a Duplex 30X50 site in E

Post by ramki067 »

m_d1982 wrote:7 Feet walls have been constructed. Lintels work to be completed by this week.

@guruprasad7 - With regards to materials used for contruction, The agreement i have with contractor is he will inform me when the new load arrives. Since i stay close in 1 km radius of the construction site i try to visit the site the same day... However with regards to wood and bathroom fittings, Electrical fittings, Flooring i will go along wwith the contractor while purchasing.. But still there are loop holes like the cement + Sand mix ratio, proper curing etc which i have to go ahead with what he says.

@Chida_gs - There are two issues i am facing with bank
1) Delay in disbursement - The problem is i have taken a loan for an axis bank approved agency ( I was not aware of this while taking the loan). Hence my request has to go through them and they receive the DD on my behalf. Lead time in them sending request to Axis bank and lead time for them to give me the DD. Eg last time it took 4 days for the agency to give me the DD.. I have approached Sr Management written to Nodal officer, Sr VP etc.. However what they say is that since i took loan through agency i have follow the same process and cannot be changed.
First disbursement they had a wrong account number on the DD and to change this it took 10 days.

2) Very less amount being approved compared to the progress made.. Right now only around 35 % of amount is approved against the actual cost incurred till now.

I will see how it works for this disbursement and decide whether to change the bank. I am paying pre emi currently for whatever amount disbursed till now.
Hi Martin,

Can i know which company steel rods and is it 500 TMT rods that you are using for pillars and the house roof slabs?

Thanks,
Ramki
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

Hi Ramki - Its Indus Steel FE500 TMT
Regards,
Martin
ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Re: Finally Started my construction a Duplex 30X50 site in E

Post by ramki067 »

m_d1982 wrote:Hi Ramki - Its Indus Steel FE500 TMT
Thanks. Whats the update from your construction?

Ramki
guruprasad7
Posts: 8
Joined: June 3rd, 2014, 4:35 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by guruprasad7 »

Thanks Martin,

Another Good News for blog members.... Even I'm starting the construction on my 30' x 50' site in Uttarahalli. :) Will start blogging the detailed information as Martin is doing, so that would help other members here.

@Martin: Thanks for the material quote you posted, i used that and modified as per my requirements and used that as a reference checker during the discussion with civil engineers. Got a best deal with my known engineer for 1.5lac for one square with overall Granite, wall claddings, Wooden carving around the pooja room door, etc, etc, etc.... will start a thread sooon :)

Drilling the borewell tomorrow @ 6am.
venkyn
Posts: 305
Joined: September 11th, 2010, 2:50 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by venkyn »

Hi GuruPrasad,

My best wishes for the construction and indeed good to know you could finalize for 1.5L.
Can you also please post the Engineer/contractor quote and the plan for the reference of members who are trying to get the financials rite.

Regards,
Venky
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

@ GuruPrasad: Congratulations and wish you all the very best. 1.5L is a good deal.

@ Ramki: Currently the first floor roof level is done. waiting for bank to disburse funds to completed the roof slab.
Regards,
Martin
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

Roof Level for First Floor
Attachments
Roof Level
Roof Level
Roof Level First Floor 2.jpg (290.87 KiB) Viewed 7225 times
Regards,
Martin
guruprasad7
Posts: 8
Joined: June 3rd, 2014, 4:35 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by guruprasad7 »

Sure Venky. I'll post it soon.
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

Centering work in Progress for First Floor Roof Slab
Attachments
Pic 3
Pic 3
Centering Work 3.jpg (238.72 KiB) Viewed 7102 times
Pic 2
Pic 2
Centering Work 2.jpg (331.69 KiB) Viewed 7102 times
Pic 1
Pic 1
Centering Work 1.jpg (275.74 KiB) Viewed 7102 times
Regards,
Martin
Post Reply

Return to “Civil Construction”