Finally Started my construction a Duplex 30X50 site in EC...
Re: Finally Started my construction a Duplex 30X50 site in E
Shuttering work and Pillar for 7Ft has been completed.
- Attachments
-
- Shuttering work before placing the pillar boxes
- Shuttering.jpg (331.43 KiB) Viewed 7198 times
-
- Pillar work, Mr Kanakaraj the contractor in White shirt
- Pillar.jpg (285.71 KiB) Viewed 7198 times
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Still waiting for the first disbursement from Axis Bank ......
I was hoping to have the major part of the external work completed before peak Monsoon. However look like there will be delays thanks to Axis Bank
Only good part is that the Contractor said he will try to do whatever possible with materials that are remaining. And try to keep the schedule.
Visited their branch in Jayanagar yesterday not much help from there, I have written email to Nodal office today...
Next steps: Just Waiting
I was hoping to have the major part of the external work completed before peak Monsoon. However look like there will be delays thanks to Axis Bank
Only good part is that the Contractor said he will try to do whatever possible with materials that are remaining. And try to keep the schedule.
Visited their branch in Jayanagar yesterday not much help from there, I have written email to Nodal office today...
Next steps: Just Waiting
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Curing the pillars using Jute sacks.. Contractor said he will do it thrice a day..
- Attachments
-
- Curing
- Curing the Pillar 2.jpg (304.81 KiB) Viewed 7139 times
-
- Alignment of the Pillars
- Pillar Alignment.jpg (330.74 KiB) Viewed 7139 times
-
- Curing
- Curing the Pillar.jpg (368.93 KiB) Viewed 7139 times
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Hi Martin,
Column boxes of 7 feet height? How did you manage to put cement concrete at the height of 7 feet ?
Also, are u going to construct in red bricks (or) cement blocks? If cement blocks, any brand decided upon?
Regards, Balaji
Column boxes of 7 feet height? How did you manage to put cement concrete at the height of 7 feet ?
Also, are u going to construct in red bricks (or) cement blocks? If cement blocks, any brand decided upon?
Regards, Balaji
Re: Finally Started my construction a Duplex 30X50 site in E
Finally got the First disbursement done by Axis Bank after a 10 days delay from when they confirmed the DD was ready.
Bought a 1 HP Taro Pump from Bomanahalli, INR 4350, 2 yrs Warranty
Today planning to go for purchasing wood with the contractor for the GF, Door and Window Frames. The wall will be constructed only after placing the Frames.
Hey Balaji - Yes we got Column boxes for 7 Feet and we put the concrete. we used a vibrator to make sure the concrete settles in completely.
We are using solid cement blocks, We are going with a cement block company very close to our plot its not a branded one like APCO or Basant.
The first lot which we received were pretty decent.
Bought a 1 HP Taro Pump from Bomanahalli, INR 4350, 2 yrs Warranty
Today planning to go for purchasing wood with the contractor for the GF, Door and Window Frames. The wall will be constructed only after placing the Frames.
Hey Balaji - Yes we got Column boxes for 7 Feet and we put the concrete. we used a vibrator to make sure the concrete settles in completely.
We are using solid cement blocks, We are going with a cement block company very close to our plot its not a branded one like APCO or Basant.
The first lot which we received were pretty decent.
- Attachments
-
- Motor for Sump
- 20140428_180732.jpg (340.12 KiB) Viewed 7077 times
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Bought Wood for GF, Doors and Windows. From timber shop on Hosa Road.
Teak - 4150 CFt
Red Sal - 1200 CFt
Total Cost - INR 46.5K
Wood will be delivered after planning latter today.
Teak - 4150 CFt
Red Sal - 1200 CFt
Total Cost - INR 46.5K
Wood will be delivered after planning latter today.
- Attachments
-
- Red sal on Left and Teak on the right side
- 20140430_101744.jpg (388.42 KiB) Viewed 7028 times
-
- Cut Piece
- 20140430_093348.jpg (312.3 KiB) Viewed 7028 times
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Poornima timbers right? Their prices are little bit less comparing to other wood dealers in hosur road stretch ( From silkboard to hosaroad).
Re: Finally Started my construction a Duplex 30X50 site in E
This was Prabhat Timbers after Jail on Hosa Road, The contractor is the regular customer there and hence he said he gets good quality at decent price.
Since we took cut pieces, We were able to choose from the lot he had. We went for Straight, Less white in Red Sal, No Pin holes in Teak.
Since we took cut pieces, We were able to choose from the lot he had. We went for Straight, Less white in Red Sal, No Pin holes in Teak.
Regards,
Martin
Martin
Re: Finally Started my construction a Duplex 30X50 site in E
Hi Martin,
Please check the Grains on the Teak wood, It is better to take the same Wood of Big Piece & cut into the Pieces as the grains will be uniform across the Pieces.
In the Cut pieces there will be a mix of grains & on the Front doors it will not look good.
Please check the Grains on the Teak wood, It is better to take the same Wood of Big Piece & cut into the Pieces as the grains will be uniform across the Pieces.
In the Cut pieces there will be a mix of grains & on the Front doors it will not look good.
Re: Finally Started my construction a Duplex 30X50 site in E
What about upvc windows instead of wooden windows is it good one or what