Steps I did, to get my building plan approval

sun
Posts: 226
Joined: March 6th, 2012, 11:46 am
Location: Bangalore

Re: Steps I did, to get my building plan approval

Post by sun »

These are the charges and exact DD amounts that I had to pay back in Aug to get the plan approval done.

Commissioner BBMP - 26000
Secretery ESB & Others - 16,250
Commissioner BBMP - 10,000
"Office Charges" - 8000
Govt. Approved Contractor to prepare the plan approval File - 2000

Overall Total - 62250/- for constructing in 30x40 site, of 2750 sqft house. In the approved document itself road cutting part is also mentioned, with that I dont have to contact anyone else anymore for paper work. Only have to obtain Occupancy Certificate after construction is complete.
biddappa_c_b wrote:Thank you Sun...yes it comes under BBMP...could you please let me know the cost you incurred? Did you pay bribe?

my site is 1400 sqft and built up areas will be 2400...

thanks
biddappa_c_b
Posts: 186
Joined: November 1st, 2011, 6:30 pm

Re: Steps I did, to get my building plan approval

Post by biddappa_c_b »

Thank you for the reply Sun. This is the below quote I got:

1) Licence Fees Rs.11700-00 Favouring The Commissioner BBMP Bangalore
2) Labour cess Rs.19,900-00 Favouring Secy Karnataka State Building & Other Construction Workers Welfare Board.
3) Road Cutting Charges Rs.16950-00 Favouring Executive Engineer Kengeri Division BBMP

bribe - 10k
Agent fees = 4 k for file prep + 3 k for getting the work done. Is this too high?
my site is 1400 sqft and built up areas shown in the plan is 2100 sqft...
biddappa_c_b
Posts: 186
Joined: November 1st, 2011, 6:30 pm

Re: Steps I did, to get my building plan approval

Post by biddappa_c_b »

Also , I applied on 23rd Sep and have to submit the DD tomorrow...and expected next weekend...its almost 1 month...despite paying "office charges" of 10k. Is this day light robbery? please reply soon
sun
Posts: 226
Joined: March 6th, 2012, 11:46 am
Location: Bangalore

Re: Steps I did, to get my building plan approval

Post by sun »

Did you check if it manual process (which is quicker, that guy just needs to put a seal and sign) or the computerized process? If it is computerized process takes a month is what I have heard from BBMP guys as applications are processed as per the Q, and you are yet to submit the DDs? These DD`s should have got into the file after someone from BBMP visits your site.
biddappa_c_b
Posts: 186
Joined: November 1st, 2011, 6:30 pm

Re: Steps I did, to get my building plan approval

Post by biddappa_c_b »

its manual process...I have already submitted the dd's..
kraghum
Posts: 152
Joined: October 8th, 2012, 4:28 pm

Re: Steps I did, to get my building plan approval

Post by kraghum »

Biddappa

I think Bribe is more assuming you are building G+1, no rental and not violating too many rules. i contacted BBMP approved Architect/Planner who gave me approval specific plan for 1500 (everything arranged in a file ) and he suggested not to go to any broker as the process will be same. i directly approached the engineer for our locality in the BBMP office (he gave me breakup costs), gave the attender Rs300 to move the files and keep track)

Engineer started with 18K, i gave 2k in beginning. i got SMS from BBMP stating my file is processes and i gave engineer another 5k since whole work is done in less than 10 days. in total paid 7k for "office charges"

FYI i stay in Hebbal and BBMP office in Sahakara nagar, my suggestion is no need of broker. directly approach the engineer or attender in office which what i did.

Raghu
sachinbr
Posts: 25
Joined: October 13th, 2013, 5:30 pm

Re: Steps I did, to get my building plan approval

Post by sachinbr »

@ kanchankumar I strongly feel Plan drafting & Online Submission by BBMP approved Architect - 30k is more. There is no rule you should submit online.
ramki067
Posts: 246
Joined: October 7th, 2009, 10:07 am

Re: Steps I did, to get my building plan approval

Post by ramki067 »

In the first post its said that "I went with the BDA supervisor". I'm very much a newbie in house construction. Hence, wanted to know as to where one needs to go with the said person to get the approval and its process?

Thanks,
Ramki
jackalbda
Posts: 371
Joined: May 5th, 2009, 9:55 am

Re: Steps I did, to get my building plan approval

Post by jackalbda »

To know who is your BDA supervisor, the best is to ask your neighbours. If nobody knows, go to the BDA office for your area and ask somebody there.
mudude12
Posts: 79
Joined: December 30th, 2013, 8:00 am

Re: Steps I did, to get my building plan approval

Post by mudude12 »

Hi,

i heard that if you want building plan approval for construction using your own funds, the expenses are far lesser ? is it true ? How is this plan approval different from the one required for bank loans ?

Please advice.

regards
Post Reply

Return to “Civil Construction”