Hi Swamy,swamy_blr wrote:Hi Friends,
From Last 2 Weeks, some progress has been made to my house construction, here are some updates.
1) Mud filling + PCC (using 40mm Jelly) has been put upto Plinth beam
......
rgds
Swamy
After mud filling, for PCC how many bags of cement was used. For my house construction(41X45 site) mestry is telling 40 bags will be required but
engineer told 80 bags required. In between some body told my father that they can finish the work with 10 bags.
engineer suggested to fill 6 inch height with PCC 40mm jelly to come tillplinth beam height. Got confused who is telling right..
can you tell me how many bags (approx) you used for your site?