Is it possible to do Front elevation after construction?

Posted: November 5th, 2015, 6:32 pm
by bestashok
Is there a possibility to do front elevation of upto 3 feet after construction?

I have already started construction for my 30X40 plot, Bangalore city, India.
And front of the building is already five feet from the pillars.
Currently building is in construction with stilt at the ground floor. First floor molding is done.

Is it possible without much rise in costs and change of building plan?

Re: Is it possible to do Front elevation after construction?

Posted: November 5th, 2015, 8:52 pm
by ausraja
Ashok , talk to your engineer/architect who are qualified to take up such challenges.

Re: Is it possible to do Front elevation after construction?

Posted: November 6th, 2015, 4:11 pm
by ardesarchitects
Hi Ashok
Front elevation is some thing to worked out along with plan .In any case front elevation can be done but with limitations .You cannot expect a form in the elevation rather cosmetic uplifting is possible .
To bring in the form or shape to elevation we might have to add few extensions to slab or chajjas , faster you get the elevation done will save money in redoing the stuff .

Regards
Ar.Praveen.N
Ardes Architects and Interior designers
ardesarchitects@gmail.com
https://www.facebook.com/ardes.architects
http://www.ardesarchitects.com

Re: Is it possible to do Front elevation after construction?

Posted: November 10th, 2015, 12:27 pm
by bestashok
Sure..sir, thanks for the suggestion.