Procedure to get new electricity connection for the site

Posted: August 24th, 2015, 2:00 pm
by maviswa
Hi,

We are planning to construct house in our site. Our site has bbmp b khatha. So can somebody let us know the procedure to get the new electricity connection? What's the process in that.

Thanks,
Maviswa

Re: Procedure to get new electricity connection for the site

Posted: August 24th, 2015, 9:30 pm
by Kiran Kumar K
hi maviswa, it is temporary connection u should take for construction purpose up to building completion & then u should take new electricity connection for the completed building. A electrician whom u have engaged for the building will take care.

Re: Procedure to get new electricity connection for the site

Posted: August 25th, 2015, 9:50 am
by msn1270
Recently I come across an article, where BESCOM says giving permanent connection later is an issue for the unauthorised layouts.
They may have to continue with the temporary connection at higher price.

Re: Procedure to get new electricity connection for the site

Posted: August 27th, 2015, 11:30 am
by arvind_aj
- I suggest to have/consult electrical contractor who will do everything for you. Of course, you have to pay him service charges. But things will become very easy.
- Go for 2-3KW connection. Monthly rental will be ~2000
- You need to submit ID proof, EC, plan sanction paper, khata paper