I have finalized one contractor over reference from this forum.
We are going ahead with agreement this week.
This will be Item rate contract, where rate over specification + labour is given by contractor for every item.
Now my concern is what all clause I need to include in agreement.
Further, How much should be mobilization advance. Work order is divided in 2 parts (Civil + Finish) costing 32 + 14 lakhs.
Contractor has asked for 8%, I plan to give 2 lakh as mobilization advance.
What worries me practically is he doesnt have any office and its purely on trust. So what all precautions should i take ?
please share your expert advice.
I have finalized one contractor over reference from this forum.
We are going ahead with agreement this week.
This will be Item rate contract, where rate over specification + labour is given by contractor for every item.
Now my concern is what all clause I need to include in agreement.
Further, How much should be mobilization advance. Work order is divided in 2 parts (Civil + Finish) costing 32 + 14 lakhs.
Contractor has asked for 8%, I plan to give 2 lakh as mobilization advance.
What worries me practically is he doesnt have any office and its purely on trust. So what all precautions should i take ?
please share your expert advice.