Toilet waterproofing....

Posted: October 5th, 2014, 11:07 pm
by sahu.mgse
Dear Members;

Urgently need to know the method adopted for waterproofing of toilet before tiles laying. What is duration to be observed for leakage/seepage. Presently contractor has cleaned the RCC slab from dust/stone and planning to do mortar filling over complete area to cover pipes. We have 5 toilets with one is sunken. He was suggesting he will use polymer coating as waterproofing .

regards
Sahu

Re: Toilet waterproofing....

Posted: October 6th, 2014, 8:28 am
by girishd
@sahu,

My project has not yet reached that stage. I have done external waterproofing of basement walls using Fosroc Brushbond RFX. This was applied in 2 coats after plastering