Posted: April 24th, 2014, 11:01 am
It’s time for the sanction plan approval and I approached my contactor to help me find the right person. He introduced me to a BBMP registered engineer and below are the things we did so far.
1. Explained him about my working plan, we discussed how the sanction plan would look like and the steps involved for approval. My questions on bylaws got clarified.
2. He explained me the breakdown of his fees, BBMP DD charges and bribing the officials.
His fees is 10k for completing the sanction plan, uploading the plan on BBM website and preparing all the documents. Also included is the estimate for bank loan. I agreed for 10k.
3. He said that BBMP Bommanahalli can’t comprise on bribe and they expect atleast 15 to 18k as bribe. I was unwilling to pay bribe, sanctioning plan comes under Sakala scheme. He too agreed on Sakala but warned me that I may have to visit BBMP Bommanahalli office 3 to 7 times. I was ok with this.
4. Since I would go with Sakala, he said that all documents needs to be precise without any mistakes. Further he visited my site to capture these data with my contactor.
Dimension of site
Width of road
Position of electric pole
Water and Sewage pipeline location.
Locality map
5. Next, we discussed how the sanction plan would look like and how it differs from Working plan. This is very important stage considering the following parameters.
a. Would you go with deviation and or illegal construction
b. Future construction plans (if any)
c. How much the BBMP DD charges comes to
d. How many kitchen and car parking are needed
e. Bribe increases with number of units
Working plan is as below
GF – 2 car parking + 2 BKH house
FF – Duplex house
SS – Duplex house continued + 1 BHK house
Sanction plan would be done this way
Stilt - Parking for 2 cars
GF and FF – Duplex house
SS – 2 BHK house
Confirmed below points as well.
a. The approved plan is valid for 2 years only.
b. BESCOM connections can be taken for 3 units and additional 1 for water motor, though the sanction plan says 2 units only.
c. When the construction commences till plinth level, the owner has to apply for commencement certificate and after completion should apply for Occupancy certificate provided the construction is done as per Sanction plan (only 5% deviation allowed) Naturally I would not be applying these
I will keep you all updated what happens next week. Right now waiting for Sanction plan to be ready, also waiting for Khata Certificate and Khata Extract which I applied this week.
1. Explained him about my working plan, we discussed how the sanction plan would look like and the steps involved for approval. My questions on bylaws got clarified.
2. He explained me the breakdown of his fees, BBMP DD charges and bribing the officials.
His fees is 10k for completing the sanction plan, uploading the plan on BBM website and preparing all the documents. Also included is the estimate for bank loan. I agreed for 10k.
3. He said that BBMP Bommanahalli can’t comprise on bribe and they expect atleast 15 to 18k as bribe. I was unwilling to pay bribe, sanctioning plan comes under Sakala scheme. He too agreed on Sakala but warned me that I may have to visit BBMP Bommanahalli office 3 to 7 times. I was ok with this.
4. Since I would go with Sakala, he said that all documents needs to be precise without any mistakes. Further he visited my site to capture these data with my contactor.
Dimension of site
Width of road
Position of electric pole
Water and Sewage pipeline location.
Locality map
5. Next, we discussed how the sanction plan would look like and how it differs from Working plan. This is very important stage considering the following parameters.
a. Would you go with deviation and or illegal construction
b. Future construction plans (if any)
c. How much the BBMP DD charges comes to
d. How many kitchen and car parking are needed
e. Bribe increases with number of units
Working plan is as below
GF – 2 car parking + 2 BKH house
FF – Duplex house
SS – Duplex house continued + 1 BHK house
Sanction plan would be done this way
Stilt - Parking for 2 cars
GF and FF – Duplex house
SS – 2 BHK house
Confirmed below points as well.
a. The approved plan is valid for 2 years only.
b. BESCOM connections can be taken for 3 units and additional 1 for water motor, though the sanction plan says 2 units only.
c. When the construction commences till plinth level, the owner has to apply for commencement certificate and after completion should apply for Occupancy certificate provided the construction is done as per Sanction plan (only 5% deviation allowed) Naturally I would not be applying these
I will keep you all updated what happens next week. Right now waiting for Sanction plan to be ready, also waiting for Khata Certificate and Khata Extract which I applied this week.