Page 1 of 1
road cutting approval - online? timing?
Posted: December 22nd, 2012, 9:30 pm
by dev13
I got the building plan approved last year in October through BBMP online plan sanction process.
Now I am at a stage doing plastering and about to start plumbing...atleast 4 months for full completion
when is a good time to apply for road cutting approval?
how long it takes to get approval after application is submitted?
should I do online or go for offline method?
please suggest.
Re: road cutting approval - online? timing?
Posted: March 8th, 2013, 10:32 pm
by dev13
I finally got this done from local BBMP office....some of you who got plan sanctioned recently and also paid for road cutting still need to get the "Endorsement" letters from BBMP AEE.
one endorsement each for BWSSB water, Sewage and BESCOM
they come and inspect violations before issuing the Endorsements.
one needs to attach the original Endorsements to BWSSB and BESCOM when applying for connections.
Re: road cutting approval - online? timing?
Posted: March 9th, 2013, 7:32 am
by sholla
Is "Endorsement" a new procedure ? When I enquired I was
told to provide copy of sanction plan, RWH photo, tax paid receipt,
copy of sales deed, building photo, BWSSB challan. There
was no mention of this "Endorsement" .
Re: road cutting approval - online? timing?
Posted: April 17th, 2013, 11:24 pm
by dev13
my plumber had asked for Endorsement original while applying for BWSSB connections. I also heard that building photo should be with whitewash.
But electrical (KEB) connection, electrician did not take Endorsement at all., so it seems there is flexibility for KEB atleast.
Re: road cutting approval - online? timing?
Posted: April 24th, 2013, 6:55 pm
by BengaluruBoy
In my case, apart from road cutting charges I had paid BWSSB charges around 16K for 40.60 site also thru syndicate bank challan at the time of plan approval.
Did you guys also pay the simila charges?
Re: road cutting approval - online? timing?
Posted: June 19th, 2013, 1:02 pm
by tendlu
Couple of quick question:
Do we have to pay for the road cutting charges at the time of applying for BBMP Plan approval or can we wait until we near construction completion to pay for the road cutting charges?
In case the road cutting charges are paid upfront during BBMP approval does it have a validity period? If so, how many months/years?
Re: road cutting approval - online? timing?
Posted: June 22nd, 2013, 1:03 am
by arjun.surendra04
Yes during the plan approval stage bbmp collects road cutting fees and will issue a challan. However in order to cut the road u will need a road cutting endorsement letter. This letter will be issued after house is nearing completion and AE will visit the site carry out inspection and measure the road again and if there is extra amount that needs to be paid he will ask u to get a dd with diff amount. However citing deviations they usually ask bribe ranging from 50k to 1 lac to issue road cutting endorsement letter. Without road cutting endorsement letter bwssb will not issue a water connection. Bescom is not asking for endorsement letter yet.
Challah for road cutting are valid as long as plan is valid. Endorsement letter validity is 6 months.