Now a days, what shall be typical item rate by civil contractor for M20 columns or slabs per cft ?
Excluding steel, but including steel bar bending, scaffolding, and all other efforts.

- nalin

Re: M20 RCC Cost...

Posted: August 27th, 2009, 1:46 pm
by ardesarchitects
Hi nalin
With ultra tech cement, fine sand,bar bending and seamless sheet centering will cost between 150/- to 175/- per cft.Price varies with quantity and quality of work.

regards
Ar.Praveen.N
Ardes Architects and Interior Designers
ardesarchitects@yahoo.co.in

Re: M20 RCC Cost...

Posted: September 16th, 2009, 11:51 pm
by ngupta
Reference of any good builder...?

Re: M20 RCC Cost...

Posted: September 18th, 2009, 11:34 am
by ardesarchitects
Hi Nalin,
Are you talking about builder to do the complete construction or just to cast the slab ?

regards
Ar.Praveen.N
Ardes Architects and Interior Designers
ardesarchitects@yahoo.co.in

Re: M20 RCC Cost...

Posted: September 19th, 2009, 10:28 pm
by ngupta
yes

Re: M20 RCC Cost...

Posted: September 20th, 2009, 2:19 pm
by ardesarchitects
Hi Nalin
Yes for what ? complete construction or just to cast the slab

regards
Ar.Praveen.N
Ardes Architects and Interior Designers
ardesarchitects@yahoo.co.in

Re: M20 RCC Cost...

Posted: July 9th, 2012, 10:39 pm
by sam_m400
Praveen this was rate during 2009, any clue how the rate is now?

Are you talking about labour or labour+material for only the RCC( RCC filling labour + sand + jelly + cement + stell + barbending + gangmen + centering) ?

Is is only the roof or for pillar/beam/lintel as well?

Re: M20 RCC Cost...

Posted: July 9th, 2012, 10:48 pm
by ardesarchitects
Hi Sam
Current rate ranges at 190/- 230/- per cft includes rcc material + centring only .Steel,bar bending, water, power separate.

Regards
Ar.Praveen.N
Ardes Architects and Interior Desinger
ardesarchitects@gmail.com
www.ardesarchitects.com

Re: M20 RCC Cost...

Posted: July 11th, 2012, 11:09 am
by sk1976
Praveen,
Could you please share prevailing per sqft plastering rate where the contractor uses Ramco 43 grade cement, river sand and takes care of scaffolding, curing.

What would be extra if lime rendering is needed for inside walls.

Thanks,
Selva

Re: M20 RCC Cost...

Posted: August 17th, 2013, 4:31 pm
by bala4034
Hello,
Can you please clarify me the rates given by my contractor is correct or not,

My building is Gr+2 in Kalyan Nagar.
Mix. M20 (Zuari Primo Cement)
RCC work including material and lobor (steel price and bending, placement cost not inclued)
Footings - 160 /CFT.
Columns, Beams, Linte, Chajja and Slabs (Gr floor to 2nd floor) - Rs. 175 to 190/CFT.
Staicase (Gr floor to 2nd floor) - Rs. 195 to 205/CFT.

Reinforcement Steel Cost (steel price and bending, placement) - Rs. 62,500 / Ton.
Basic Steel Price Rs. 46000/Ton. (Prime Gold TMT)