I am planning a G=3 on a 60 * 40 plot. Planning to use a Labor Contractor for the same and hve received the following Quotation for the structure
1. 10’X10’= 100sft, Roof to roof
measurement including Centering work
and bar bending work
34,000/-
2. Sump tank work extra per litre 8.00/-
3. Overhead tank extra roof
measurement
0.00/-
4. Compound work extra per square feet `: 70.00/-
5. Drainage Chappadi stone work extra
per Square feet
`: 80.00/-
6. Parapet wall per Square feet : 70.00/-
7. Terrace work Per Square feet : 0.00/-
8. All Material Including scaffolding work
and Material like sarve hagga sponge
is contractor responsibility
`: 0.00/-
9. Drum, Bucket, Every Sunday curing
payment, earth work, soil filling owner
responsibility
10. No major work day curing payment
daily
`: 450.00/-
11. Watch man salary per Month `:
3,500.00/-
Payment schedule as per below:
1. Plinth and column raising and centering advance: `: 1,75,00.00/-
2. Ground Floor Slab : `: 3,00,00.00/-
3. First Floor Slab : `: 3,00,00.00/-
4. Second Floor Slab : `: 3,00,00.00/-
5. Third Floor Slab : `: 2,30,00.00/-
6. Staircase and Lift Room : `: 1,00,00.00/-
7. Ground Floor wall Construction : `: 40,00.00/-
8. First Floor wall Construction : `: 90,00.00/-
9. Second Floor wall Construction : `: 90,00.00/-
10. Third Floor wall Construction : `: 60,00.00/-
11. Lift Floor wall Construction : `: 35,00.00/-
12. Plastering Sarve Advance : `: 40,00.00/-
13. Ground Floor Plastering : `: 30,00.00/-
14. First Floor Plastering : `: 50,00.00/-
15. Second Floor Plastering : `: 50,00.00/-
16. Third Floor Plastering : `: 50,00.00/-
17. Lift Room And Staircase Plastering `: 40,00.00/-
18. Outside East Plastering `: 50,00.00/-
19. Outside West Plastering `: 50,00.00/-
20. Outside North Plastering `: 50,00.00/-
21. Outside South Plastering `: 50,00.00/-
Grand Total: `: 22, 20, 00.00/-
Have a Architect appointed; need some feedback on what else is missing in the contract terms.
Will be highly appreciative if I can get some insights into this process.
Thanks
Labor Contract: Quotation Feedback
Re: Labor Contract: Quotation Feedback
Hi msg5555,
Firstly congrats that you are commencing the construction of new house. To comment anything about your Labour contract part first I need to know for how much built-up area he is quoting 22 lakhs and again construction is of cement blocks or Red bricks which matters a lot.
In current market if cement blocks then Rs 28K for 100sqft is ideal price including compound wall as well, only extra thing would be charged is water sump if RCC, chain link staircase and elevation. For RCC sump you should negotiate based on lump sum amount, to give actual figures for RCC sump of 25K litre capacity I would say 40 to 50k is ideal price. Chain link steps I think anyway between 1000 to 1500 per step would be nominal price and for elevation it depends upon design which can be again negotiated in lump-sum amount. So, in case red bricks 32K to 33K is the ideal price in the current market and rest remains same.
Firstly congrats that you are commencing the construction of new house. To comment anything about your Labour contract part first I need to know for how much built-up area he is quoting 22 lakhs and again construction is of cement blocks or Red bricks which matters a lot.
In current market if cement blocks then Rs 28K for 100sqft is ideal price including compound wall as well, only extra thing would be charged is water sump if RCC, chain link staircase and elevation. For RCC sump you should negotiate based on lump sum amount, to give actual figures for RCC sump of 25K litre capacity I would say 40 to 50k is ideal price. Chain link steps I think anyway between 1000 to 1500 per step would be nominal price and for elevation it depends upon design which can be again negotiated in lump-sum amount. So, in case red bricks 32K to 33K is the ideal price in the current market and rest remains same.
Re: Labor Contract: Quotation Feedback
Thanks Manohar.
Liking for Red Bricks. Will make sure I update the other items in the contract as well.
Liking for Red Bricks. Will make sure I update the other items in the contract as well.