House construction in whitefield

ragalax
Posts: 35
Joined: January 7th, 2018, 7:32 pm

Re: House construction in whitefield

Post by ragalax »

sunil18vns wrote:Writing review after a long time since i started construction...work started on 22 Nov 19 and now G plus 3 building of around 5800 sft entire structure is ready...cud not post pictures for now...plastering also done for ground n 1st floor...my contractor has put 9 masonary people n work is going very fast....he has multi tasked work n aim to complete entire work by Apr along with full finish...truely lucky to get a right professional team with such a great dedication.....will share more updates....next step is to buy tiles so searching dealers for it .....
In 3 months 4 slabs including the footings! try to leave some time for curing and settling, this is not the right speed. Mason may be ready to do it faster but minimum 21 day time is required for curing/settling on any concrete work, According to me the you should have taken 6 months to come to this stage!
sunil18vns
Posts: 61
Joined: February 10th, 2013, 10:06 am

Re: House construction in whitefield

Post by sunil18vns »

With 53 grade cement, it sets faster 2 weeks of centering is fine, i hardly see any challenge so far...curing still happens for all floors...
User avatar
ardesarchitects
Posts: 1080
Joined: June 20th, 2009, 2:12 pm

Re: House construction in whitefield

Post by ardesarchitects »

Hi, Sunil
Its very well appreciated that contractor is taking up work faster with out loosing time. Most cases fast work is possible when the design is typical style floor plans / straight slabs . Few things to be taken care while doing a faster work.
1.Beam lines to be matched from floor to floor to avoid higher plastering thickness
2.Since plastering started in ground floor i would say its just 30% of work happened till date , issues will pop up as the finishing works starts. Mason work is done by 50% only so accordigly payments to him should be monitored .
3.Staircase lines & risers height to be checked by tile layer befor plastering to be done
4.All room corners to be checked by tile layer to avoid skews in the tile laying, In case of any minimal skews in the corners can be adjusted in the wall plaster .
5.Window and door edges to be checked for 90degree angles
6. Plumber to be brought in to check the levels before external plastring work starts .

Regards,
Ar.Praveen.N
Ardes Architects and Interior designers
ardesarchitects@gmail.com
www.ardesarchitects.com
https://www.instagram.com/ardesarchitects
sunil18vns
Posts: 61
Joined: February 10th, 2013, 10:06 am

Re: House construction in whitefield

Post by sunil18vns »

Thanks all of you...my building is now rented ...i used to hear that building a house is nightmare but for me everything was really smooth...it all matters that you get a good contractor and his workers. Of course we need to spend our time as well. Gosh...really grateful to God for getting here without any pain..
Post Reply