NEXT WORK TO BE PLANNED

Post Reply
keerthi2006
Posts: 103
Joined: April 21st, 2016, 3:35 pm

NEXT WORK TO BE PLANNED

Post by keerthi2006 »

Hi All,

Currently, basement work have been completed by the engineer. I have purchased wood as well for my doors and windows.

Next brick work is going to start in my consturction. can you tell me what are the other things i should plan right now for my construction in advance.

Any idea would be appreciated. since i am starting my construction first time. i dont know what are the things to be planned first.

please help me out what are the things to be planned before the brick work getting started. since i am having adequate timings i can plan the next step in advance to get a good result.

Thanks,
KK
REVA
Posts: 8
Joined: September 1st, 2015, 11:08 am

Re: NEXT WORK TO BE PLANNED

Post by REVA »

Not a direct answer, but found this list on interwebs; which might help you :D
  1. Site cleaning
  2. Bore well digging
    1. Bore Well vendors Quotes, finalization
    2. Bore
  3. Temporary Shed construction
  4. Site Marking
  5. Sump construction
    1. Soil digging for sump
    2. Sump Construction
  6. Foundation digging
    1. Soil digging for Pillars
    2. Soil digging for foundation [OR] Paya
  7. Start carpenter work/purchase — for window frames and door frames
  8. Footing [OR] Pillar base
  9. Pillars until Plinths
  10. Stone Foundation [OR] paya
  11. Plinth beam
  12. Fill soil inside Plinth area.
  13. Filling 40 MM Jelly on top of Soil — this will be done inside Plinth area
  14. Setting up main door frame and other room door frames
  15. Wall construction until window frame base (Approximately around 3 feet)
  16. Setup all window frames based on its sizes until 7 feet from the flooring
  17. Setup lintel and Sajja
  18. Wall construction until beams
  19. Setup kitchen ventilators for exhaust fans OR bathroom ventilators if needed
  20. Sheet centering for beams and also roof
    1. Fix sheets based on water level
    2. Apply plaster for the gaps between sheets
    3. Apply oil for sheets
  21. Bar bending work for beams and roof
    1. Inverter beams
  22. Electric pipes setup inside roof
  23. Molding
  24. Storing water on top of the roof
  25. After 18 days remove sheet centering
  26. Hocking for the roof
  27. Electric pipes
  28. Clear any blockage in the roof pipes
  29. Laying electric pipes in the walls and setup electric boxes
  30. Plumbing work for kitchen and bathroom
    1. Setup water pipes and sewage pipes till outside of the wall
    2. Setup Indian latrine if you are going with this option
    3. Water proofing for bathrooms
    4. Close all water and sewage pipes with temporary caps
  31. Setup kitchen platform and sink
  32. Tiles laying in bathroom and kitchen for walls
  33. Plastering of roof and walls inside
  34. Plastering of outside walls
  35. Applying putty for window frames
  36. Fixing window frames
  37. Granite Lying
  38. Granite tiles Laying in bathroom if you are going with this option
  39. Fixing bathroom fittings
  40. Finishing outside plumbing work and tank
  41. House Elevation
  42. Painting
  43. Electric work
    1. Electrical wiring
    2. Dummy plate fixing/ electrical holders
    3. Electrical switches setup
  44. Apply paint coating outside
  45. Laying electric service wire from pole to meter board
  46. Fixing meters in panel board.
  47. Digging pit for power earth
  48. Digging pit
  49. Motor & connection to tank
  50. Sewage lines to pit
  51. Parking tiles
  52. Compound wall
keerthi2006
Posts: 103
Joined: April 21st, 2016, 3:35 pm

Re: NEXT WORK TO BE PLANNED

Post by keerthi2006 »

hi all,

Currently, I am in step 12. filling the soil in the plinth area.
Post Reply

Return to “Civil Construction”