Hi All,
Currently, basement work have been completed by the engineer. I have purchased wood as well for my doors and windows.
Next brick work is going to start in my consturction. can you tell me what are the other things i should plan right now for my construction in advance.
Any idea would be appreciated. since i am starting my construction first time. i dont know what are the things to be planned first.
please help me out what are the things to be planned before the brick work getting started. since i am having adequate timings i can plan the next step in advance to get a good result.
Thanks,
KK
NEXT WORK TO BE PLANNED
-
- Posts: 103
- Joined: April 21st, 2016, 3:35 pm
Re: NEXT WORK TO BE PLANNED
Not a direct answer, but found this list on interwebs; which might help you
- Site cleaning
- Bore well digging
- Bore Well vendors Quotes, finalization
- Bore
- Temporary Shed construction
- Site Marking
- Sump construction
- Soil digging for sump
- Sump Construction
- Foundation digging
- Soil digging for Pillars
- Soil digging for foundation [OR] Paya
- Start carpenter work/purchase — for window frames and door frames
- Footing [OR] Pillar base
- Pillars until Plinths
- Stone Foundation [OR] paya
- Plinth beam
- Fill soil inside Plinth area.
- Filling 40 MM Jelly on top of Soil — this will be done inside Plinth area
- Setting up main door frame and other room door frames
- Wall construction until window frame base (Approximately around 3 feet)
- Setup all window frames based on its sizes until 7 feet from the flooring
- Setup lintel and Sajja
- Wall construction until beams
- Setup kitchen ventilators for exhaust fans OR bathroom ventilators if needed
- Sheet centering for beams and also roof
- Fix sheets based on water level
- Apply plaster for the gaps between sheets
- Apply oil for sheets
- Bar bending work for beams and roof
- Inverter beams
- Electric pipes setup inside roof
- Molding
- Storing water on top of the roof
- After 18 days remove sheet centering
- Hocking for the roof
- Electric pipes
- Clear any blockage in the roof pipes
- Laying electric pipes in the walls and setup electric boxes
- Plumbing work for kitchen and bathroom
- Setup water pipes and sewage pipes till outside of the wall
- Setup Indian latrine if you are going with this option
- Water proofing for bathrooms
- Close all water and sewage pipes with temporary caps
- Setup kitchen platform and sink
- Tiles laying in bathroom and kitchen for walls
- Plastering of roof and walls inside
- Plastering of outside walls
- Applying putty for window frames
- Fixing window frames
- Granite Lying
- Granite tiles Laying in bathroom if you are going with this option
- Fixing bathroom fittings
- Finishing outside plumbing work and tank
- House Elevation
- Painting
- Electric work
- Electrical wiring
- Dummy plate fixing/ electrical holders
- Electrical switches setup
- Apply paint coating outside
- Laying electric service wire from pole to meter board
- Fixing meters in panel board.
- Digging pit for power earth
- Digging pit
- Motor & connection to tank
- Sewage lines to pit
- Parking tiles
- Compound wall
-
- Posts: 103
- Joined: April 21st, 2016, 3:35 pm
Re: NEXT WORK TO BE PLANNED
hi all,
Currently, I am in step 12. filling the soil in the plinth area.
Currently, I am in step 12. filling the soil in the plinth area.