Recent Borewell charges.

mohanraj2
Posts: 2
Joined: September 3rd, 2012, 3:09 pm

Re: Recent Borewell charges.

Post by mohanraj2 »

My luck, the casing went upto only 80 feet. Some borewell goes beyond 140-150 ft. That will cost you more.

below is the actual:

0 300 300 65 19500
300 400 100 75 7500
400 500 100 85 8500
500 600 100 100 10000
600 700 100 115 11500
700 800 100 135 13500
800 810 10 165 1650
Borewell = 72150
Casing 260* 80 = 20800
Coller 100* 7 = 700
Weilding 100* 7 = 700
Meal = 500
Transport = 500
avipnv
Posts: 29
Joined: September 24th, 2013, 1:13 pm

Re: Recent Borewell charges.

Post by avipnv »

Hello Mohanraj,

Thanks for the this information, i plan to get a borewell dug at JP Nagar 7th phase, kindly let me know the
borewell company name and contacts.

Regards
Avinash
arunthl
Posts: 102
Joined: August 3rd, 2011, 2:07 pm

Re: Recent Borewell charges.

Post by arunthl »

Me too.. can u pls let me know the company name and also if they have the geologist..
chetand
Posts: 13
Joined: November 5th, 2012, 1:05 pm

Re: Recent Borewell charges.

Post by chetand »

My suggestion would be to go with other borwell drillers as chances are you may need to go in depth depending upon your topography you always need to have the flexibility for going in depth to ensure you get source.
kr_sunny
Posts: 2
Joined: March 9th, 2012, 12:12 pm

Re: Recent Borewell charges.

Post by kr_sunny »

HI Mohanraj/Vkalavar

Iam planning to construct house in Hormavu(nearby to Rammurthynagar)....I would need reliable borewell contractor...I read this post and was curious about Sri Manjunath borewells...Is this vendor good and come on time....cost looks very reasonable though

I would appreciate your help in this regard

Thanks
Sunil K R
Post Reply

Return to “Civil Construction”