I have received the following contractor quotation and specification
  • Red Brick wall with pillar construction
    floor tiles : 60/Sq Ft
    wall tiles: 35-40Rs /Sq ft
    Electrical : Conceled wiring Finolex Wires, Norwood switches
    Kitchen : Granite kitchen platform for 20Ft*3Ft, Kitchen wall tiles for 20Ft length and 7th ft height
    Bathroom : wall tiles 7 ft, Jacquar fitting with solar heater, electrical heater lines, CPVC pipes and outlet pipes are finolex
    Main door & frame : Burma teak with 6*4 with Antique fitting, godrej lock
    All other frames and window shutters are White Teak and all other doors plush doors
    Electrical points : standard requirements with one Bed room with AC point
    Terrace : Weather proofing with 2.5 ft parapet wall
    Overhead Loft in kitchen and bedrooms of 7 ft length and 2.5 ft width
    Internal walls : 1 coat white cement and 2 coat emulsion
    External walls : similar emulsion
Additional
  • Any wood work
    Gate on the compound wall
    Electrical fittings (fan, light etc)
    Sump & Septic tank - 50% of the sq ft rate
    Steps - 75% of sq ft rate. Steps will be finished with step tiles
    Compound wall 250/Sq Ft (includes foundation) for a 6" red block work with plastering
Cost per sq ft Rs. 1400 per Sq. Ft

looking for experts opinion on the following
1. Is the sq ft cost quoted reasonable?
2. Is it a standard practice to charge 50% for the sump/septic tank and 75% for steps
3. Portico/lintel(sun shade) are included for the sq ft calculation - Is this usual practice?

Thanks in advance
vmuralictr
Posts: 56
Joined: August 31st, 2012, 8:22 am
Contact:

Re: Contractor Quotation for House construction

Post by vmuralictr »

I think this rate looks reasonable
biddappa_c_b
Posts: 186
Joined: November 1st, 2011, 6:30 pm

Re: Contractor Quotation for House construction

Post by biddappa_c_b »

Hi All,
Am planning to construct a gf+ff+sf(sf will have only one bedroom and staircase headroom). Am planning to go with Clayblocks throughout with the exception of Stone in the elevation.(total built up area will be 2400)
Could someone please let me know whether the below rates are reasonable:
1. Providing size stone masonary in super structure using hammered dressed stones on one face with CM 1:6 upto plinth level = 125 rs/cft
2. Conbstructing size stone masonary in super structure in CM 1:6 with neatly chiseled dressed size stone on both the sides = 375 rs/cft
3. Providing and constructing 9" thick brick masonary in super structure with Cm 1:6 using best quality table moulded bricks : GF = 185 Rs/cft, FF = 195 Rs/cft, SF = 205 Rs/cft, Paraphet wall = 205 Rs/cft
4. 4 1/2 " thick partition walls in CM 1:4 at all floors: 100 Rs/cft
5. Hollow clay block masonary in CM 1:6 8" thick at all floors = 190Rs/sft
6. Roof Slab 6" thick with filler block = 200 Rs/sft

Need urgent help.