Plumbing Question

Vimal
Posts: 124
Joined: December 9th, 2009, 10:43 am

Re: Plumbing Question

Post by Vimal »

Mahesh,

Both are wrong. You need two lines to the chamber (one line for 4" pipe and another line for 2-1/2" pipe)

Vimal.
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Plumbing Question

Post by maheshvivid2003 »

thanks guys

he has done the same thing to all the bathroom and he had put concrete on to pipes only the has to connect the outside pipes

if i tell him to re do the complete work them he has remove all the things and has to redo it ....in this case he will ask for more money and also it will be a waste of materials 9 bath quite a lot of money

in this case wat should i do ?
will ther be a major problem in future?
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Plumbing Question

Post by maheshvivid2003 »

hi guys im looking for ur adive n suggestions ?
User avatar
jult
Posts: 120
Joined: July 21st, 2012, 3:42 pm

Re: Plumbing Question

Post by jult »

Dear Mahesh,
Please provide a Gully chamber before connecting to the main chamber. your problem will be solved. Dont connect pipe to the chamber.
BengaluruBoy
Posts: 210
Joined: June 18th, 2009, 1:27 pm

Re: Plumbing Question

Post by BengaluruBoy »

Mahesh - I had the same problem. out of 5 bathrooms he had done 2 sep lines for 3 bathrooms. I forced him to cut concrete/wall to redo the separate lines for atleast our master bath. For the other one which was at second floor i just left it like that since it was too difficult to do based on our bathroom design.

my architect also insisted on 2 separate ilnes.
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Plumbing Question

Post by maheshvivid2003 »

thanks guys i really appreciate it

for every sanitary pipe outlet ther will be chambers and corners also so totally 5 chan\mbers will be ther and for ground he will be using 6inch pipe

discussed with him he is asking more money and his reason is that now a days most of the people do the samething

labour and materia would cost me more now ...decision is still pending
maheshv
Posts: 220
Joined: September 7th, 2010, 9:32 pm

Re: Plumbing Question

Post by maheshv »

Mahesh,i think you should go for different lines, though it will cost you some amount now, it is better than getting bad smell every now and then when you live in that house.

Also my plumber suggest that now a day they get a clamp which keeps sanitary pipe lines 3 inch away from the wall (vertical lines), this will be good in case there is a leakage as wall will not get affected by the leakage. Sharing this info for the benefit of all
maheshvivid2003
Posts: 370
Joined: January 24th, 2012, 11:57 am

Re: Plumbing Question

Post by maheshvivid2003 »

thanks mahesh

luckily we have used clamps for pipes
mcs
Posts: 13
Joined: January 16th, 2013, 8:10 pm

Re: Plumbing Question

Post by mcs »

hi vimal.,
immediately remove the conncetion, soil waste to be connected through separate line ( 1st /2nd floor waste pipes he can connect, not the wash/shower line)

Raju