labour contract for centering work & shuttoring

Post Reply
semmalai
Posts: 4
Joined: March 15th, 2013, 11:01 am

labour contract for centering work & shuttoring

Post by semmalai »

One of contractor said 48 psft for centering work and shuttering .is it correct rate ? mine is 1100 sqft
kpb2308
Posts: 78
Joined: October 3rd, 2011, 11:57 am

Re: labour contract for centering work & shuttoring

Post by kpb2308 »

48 psft? How does he measure the sft? Is it just the plinth area, or will he measure the roof, each side of beam etc?
I am paying Rs. 25/per sft for roof, and arnd 27/sft for beam.
semmalai
Posts: 4
Joined: March 15th, 2013, 11:01 am

Re: labour contract for centering work & shuttoring

Post by semmalai »

The rate is based on the plinth area. my site is 28.25 * 39 .So i need to pay 1115(28.25*39) *48. This rate includes the column,beam,roof ,stair case,loft etc
m3_07
Posts: 299
Joined: November 7th, 2011, 7:50 am

Re: labour contract for centering work & shuttoring

Post by m3_07 »

semmalai wrote:One of contractor said 48 psft for centering work and shuttering
This price is extremely high. Normally it is around 28 - 30 rs/ SFT. This price remains the same for G + 1. From 2nd floor onwards, it goes up by 2 to 5 Rs/ SFT.
semmalai
Posts: 4
Joined: March 15th, 2013, 11:01 am

Re: labour contract for centering work & shuttoring

Post by semmalai »

for 28 weather it include column,plinthbeam,lintelbeam,loft ,stair case.... how the measure the SFT
mohan_hu
Posts: 71
Joined: August 18th, 2011, 12:33 pm

Re: labour contract for centering work & shuttoring

Post by mohan_hu »

Its 24 Rs to 30 Rs based on which floor you are doing the centering. For Example.

Ground Floor - 24 Rs
Ist Floor - 26 Rs
2nd and 3 rd Floor 28 Rs.
semmalai
Posts: 4
Joined: March 15th, 2013, 11:01 am

Re: labour contract for centering work & shuttoring

Post by semmalai »

mohan_hu wrote:Its 24 Rs to 30 Rs based on which floor you are doing the centering. For Example.

Ground Floor - 24 Rs
Ist Floor - 26 Rs
2nd and 3 rd Floor 28 Rs.

weather it include shuttering , how they are measering sqft (plinth area / ?)
m3_07
Posts: 299
Joined: November 7th, 2011, 7:50 am

Re: labour contract for centering work & shuttoring

Post by m3_07 »

SFT is measured for the area where the plates are installed & it does include everything. The RCC column boxes have a separate rentals & is not calculated in SFT, rather in the height of the box.