Page 1 of 1

Completion Certificate Application process for Independent house

Posted: October 16th, 2018, 8:27 am
by srivatsahg
Hello
What is the procedure to apply for the Completion Certificate for an independent house coming under BDA
Any idea about the document pre-requisites before applying for the same.

Re: Completion Certificate Application process for Independent house

Posted: November 28th, 2018, 9:07 am
by duffyhair
is there one? I doubt.. I submitted the electricity bill and a letter from the registered architect as completion certificate, it was accepted..

Re: Completion Certificate Application process for Independent house

Posted: March 18th, 2019, 12:02 pm
by kunalsd
Hello,
Need to know if Commencement, Completion & Occupation Certificates are necessary for an individual duplex house[in a BDA approved layout] with just one family residing.
Thanks in advance.

Kunal

Re: Completion Certificate Application process for Independent house

Posted: March 18th, 2019, 2:47 pm
by msn1270
Per my knowledge, Houses built below 60X40 dimension sites, doesn't need Completion & Occupancy Certificates as per BBMP Rule and you can avail the BESCOM & BWSSB Connections.

Re: Completion Certificate Application process for Independent house

Posted: March 18th, 2019, 3:36 pm
by kunalsd
msn1270 wrote:Per my knowledge, Houses built below 60X40 dimension sites, doesn't need Completion & Occupancy Certificates as per BBMP Rule and you can avail the BESCOM & BWSSB Connections.
Thanks MSN !

So "Commencement Certificate" is needed for all dimension sites.

Can you let us know the process to apply/procure it & fee structure involved.

Thanks,
Kunal