BDA Kempegowda Layout Development Status

Posted: December 29th, 2017, 5:28 pm
by originalamit
This thread is to update everyone on the current state of the layout and where BDA is with respect to development of layout
#BDA
#Kempegowda
#layout
#government
#development
#Bangalore
#Kempegowda Layout
#status
#block

Re: BDA Kempegowda Layout Development Status

Posted: December 29th, 2017, 5:39 pm
by originalamit
Phase 1 of Kempegowda layout lacks development currently. Its been over 2 years and the land has become barren forest land again. Only 2 roads are being done. Hoping the BDA does develop this layout.

Now they have announced another phase2 of the layout. Hard to understand why another layout when current one itself has no development and BDA says no money left.

Photos of Block 7 taken on December 28th, 2017. Please see for yourself
2017-12-29-PHOTO-00003019.jpg
2017-12-29-PHOTO-00003019.jpg (130.25 KiB) Viewed 27053 times
2017-12-29-PHOTO-00003018.jpg
2017-12-29-PHOTO-00003018.jpg (65.58 KiB) Viewed 27053 times
2017-12-29-PHOTO-00003016.jpg
2017-12-29-PHOTO-00003016.jpg (70.79 KiB) Viewed 27053 times
#BDA
#BAngalore Development Authority
#Kempegowda Layout
#Nandaprabhu

Re: BDA Kempegowda Layout Development Status

Posted: December 29th, 2017, 5:46 pm
by originalamit
Block 5 status as on 25th December, 2017

All of this has again become forest land after layout development was announced 2 years ago. BDA . has not yet registered for KRERA act
IMG_2577.JPG
IMG_2577.JPG (286.28 KiB) Viewed 27053 times
IMG_2574.JPG
IMG_2574.JPG (240.67 KiB) Viewed 27053 times
IMG_2573.JPG
IMG_2573.JPG (242.19 KiB) Viewed 27053 times
#BDA
#BAngalore Development Authority
#Kempegowda Layout
#Nandaprabhu

Re: BDA Layout Development Status

Posted: December 29th, 2017, 5:49 pm
by originalamit
Block 2 status as on 24th December, 2017

Again, you can see that no approach road, no layout development of any kind has happened. Only 2 roads have got development started across entire layout which is about 7 blocks!
IMG_2581.JPG
IMG_2581.JPG (212.53 KiB) Viewed 27053 times
IMG_2582.JPG
IMG_2582.JPG (346.45 KiB) Viewed 27053 times
IMG_2585.JPG
IMG_2585.JPG (324.52 KiB) Viewed 27053 times
#BDA
#BAngalore Development Authority
#Kempegowda Layout
#Nandaprabhu

Re: BDA Kempegowda Layout Development Status

Posted: December 29th, 2017, 6:26 pm
by originalamit
Other blocks situation. Images taken in December, 2017
IMG_2588.JPG
IMG_2588.JPG (242.72 KiB) Viewed 27031 times
IMG_2587.JPG
IMG_2587.JPG (450.67 KiB) Viewed 27031 times
IMG_2586.JPG
IMG_2586.JPG (498.34 KiB) Viewed 27031 times

Re: BDA Kempegowda Layout Development Status

Posted: December 29th, 2017, 6:28 pm
by originalamit
News articles on the layout
IMG_2591.JPG
IMG_2591.JPG (255.45 KiB) Viewed 27029 times
IMG_2590.JPG
IMG_2590.JPG (367.62 KiB) Viewed 27029 times
IMG_2589.JPG
IMG_2589.JPG (295.28 KiB) Viewed 27029 times

#BDA
#BAngalore Development Authority
#Kempegowda Layout
#Nandaprabhu
#status

Re: BDA Kempegowda Layout Development Status

Posted: December 30th, 2017, 7:59 am
by originalamit
There is a waste processing unit in the layout whose smell goes across all phases of it and the stench is really bad.. it happens on certain days of the week

https://timesofindia.indiatimes.com/cit ... =TOIMobile

BDA Called for Kempegowda Layout Phase 2

Posted: December 31st, 2017, 11:47 am
by raghu_pro
BDA called for New applications for Phase 2
Last date 09-02-2018

Re: BDA Called for Kempegowda Layout Phase 2

Posted: December 31st, 2017, 5:58 pm
by rakesh_npkl
raghu_pro wrote:BDA called for New applications for Phase 2
Last date 09-02-2018
How can they announce new layout when they are not registered with KRERA? Its illegal and can be challenged in court. As per law, you cannot advertise or launch any project if you dont register with RERA

Re: BDA Kempegowda Layout Development Status

Posted: January 3rd, 2018, 9:32 pm
by ppb14